Multi-level white parking garage with a glass-front building and 'Welcome to Edinburgh' sign above the entrance region.

Edinburgh Airport Multi-Storey Car Park

Structural Investigation and Post-Tensioning Special Investigation

Interspan has completed a comprehensive structural investigation of Edinburgh Airport’s Terminal Multi-Storey Car Park, providing detailed information to support the ongoing management of this important airport asset.

Constructed in 2004, the five-storey post-tensioned concrete car park comprises 150mm post-tensioned slabs spanning approximately 7.5m onto 525mm-deep post-tensioned band beams, which span approximately 15.6m between reinforced-concrete columns.

Now approaching the middle of its design life, the highly utilised structure required a detailed assessment to establish its current condition and to provide an evidence base for future monitoring, maintenance and asset management decisions.

Project Overview

Location: Edinburgh, UK
Asset Owner: Edinburgh Airport
Contractor: Scott Signs
Consulting Engineer: Tony Gee and Partners
Structure: Post-tensioned slabs and beams with reinforced concrete columns
Scope: Structural investigation and Post-Tensioning Special Investigation (PTSI)

An Investigation-Led Approach

Interspan was appointed to undertake a comprehensive investigation combining non-destructive testing, targeted intrusive investigation and specialist Post-Tensioning Special Investigation techniques.

The investigation included:

  • Close visual inspection, crack mapping and delamination surveys to slabs, beams, columns and waterproofing membrane
  • Ground Penetrating Radar (GPR) to establish reinforcement and tendon locations and verify the existing construction
  • Half-cell potential surveys to assess the probability of reinforcement corrosion
  • Ultrasonic Pulse Echo (UPE) surveys to identify anomalies, concrete voids and potential defects associated with grouting of the PT ducts
  • Chloride and carbonation testing
  • Targeted reinforcement breakouts
  • Specialist Duct Tendon Exposures (DTEs) to inspect PT ducts, grout and prestressing strands
  • Sampling and laboratory analysis of concrete and PT grout
  • Assessment and recording of reinforcement and prestressing steel condition

The PTSI was undertaken to establish the condition of the post-tensioning system at critical locations, assess deterioration and corrosion risk and provide information for the structural appraisal. The investigation was carried out in accordance with Design Manual for Roads and Bridges CS 465.

Using NDT to Target Intrusive Investigation

A key element of Interspan’s methodology was the use of non-destructive testing to inform and target subsequent intrusive investigation.

GPR was used to verify tendon and reinforcement arrangements, particularly where existing as-built information was incomplete. UPE was then used to identify potential anomalies associated with the post-tensioning system.

This allowed targeted opening-up to concentrate on locations where further physical investigation would provide the greatest value, enabling the project team to establish actual conditions, obtain material samples and develop a more informed understanding of the structure.

Working Within a Live Airport Environment

All investigation works were undertaken within an operational airport car park.

Careful segregation, traffic management and daily coordination were required to minimise disruption to airport operations and members of the public. The works were also programmed around operational requirements, including a break over the Easter holiday period so the car park could remain fully available during a particularly busy period.

More Than 1,350 Investigation Locations Digitally Recorded

Interspan recorded the investigation using a cloud-based digital twin, providing Edinburgh Airport and Tony Gee and Partners with live access to information as it was collected.

More than 1,350 individual investigation locations were digitally recorded, allowing photographs, test results and condition classifications to be reviewed against their precise position within the structure.

This provided a detailed and accessible record of the investigation and an evidence base for ongoing structural assessment and asset management.

Supporting Long-Term Asset Management

By combining specialist knowledge of post-tensioned structures with non-destructive testing, intrusive investigation, materials testing and digital data capture, Interspan provided the project team with a detailed understanding of the condition of both reinforced and post-tensioned elements.

The investigation provides Edinburgh Airport and its consulting engineer with the information required to assess deterioration mechanisms and corrosion risk, and to develop an informed strategy for future monitoring, repair, and long-term management of the structure.

Interspan > Investigate. Diagnose. Design. Strengthen. Protect. Extend Service Life.

Interspan 

Interspan uniquely integrates in-house post-tensioning expertise, advanced forensic diagnostics, and cutting-edge strengthening technologies to enable a single-source delivery model trusted by global developers for complex retrofit and reuse projects.

NEW STRUCTURES

The Interspan Group brings unique expertise in post-tensioning, construction methodology, and lifting operations that reduce CO₂ emissions, material usage, and construction program.

EXISTING STRUCTURES

We specialise in helping clients extend the lifespan of concrete structures through advanced repair, strengthening, and carbon-fibre solutions. Adaptive reuse projects are a perfect fit for our expertise, helping to minimise waste while delivering safe, modern outcomes that support community growth.

Over the last decade, the Interspan Group has become a market leader in adaptive reuse solutions, with notable projects including the award-winning The Space House in London and the Quay Quarter Tower in Sydney.

Quality Assurance

Quality Assurance holds immense significance for Interspan because it impacts the safety of our operatives and future occupants, the long-term durability of our structures, and our client satisfaction and relationships.

In the UK, Interspan is accredited under CARES PT 02 – Supply and installation of PT systems in concrete structures, CARES PT 04 – Supply and installation of bar PT systems in concrete structures and BS EN ISO 9001:2015 Quality management system certification and is a Constructionline Gold Member.

In Australia, Interspan is accredited under CARES APTO1 for the Production and Supply of Post-tensioning Anchorage Systems and is the only post-tension contractor in Australia accredited under CARES APTO4 for the supply and installation of Post-tensioning systems in concrete structures.

Sustainability

Post-tensioning and adaptive reuse are powerful design approaches that reduce material use and embodied carbon – delivering more efficient, resilient, and sustainable structures for the future.

Read More