Post-Tensioning Bar for Greenland Centre, Sydney
The Greenland Centre Sydney is one of the city’s most ambitious adaptive reuse projects — transforming a 1960s 29-storey commercial tower into a 70-level residential high-rise. The redevelopment involved the selective demolition of the upper portion of the existing structure, while 26 levels were retained and integrated into the new tower. A complex outrigger system was designed to effectively transfer loads between the new and existing structural elements, ensuring performance, safety, and durability.
Interspan’s Post-Tensioning System for this Adaptive Reuse Tower
Interspan was engaged to design and deliver a high-capacity post-tensioning bar system for the critical outrigger connection between Levels 26 and 28.
Our scope included the supply, installation, stressing, and grouting of 1,200 metres of 75mm diameter post-tensioning bars, linking the outrigger beam to the building’s core.
Through careful coordination and precision installation within a confined, high-rise environment, Interspan delivered a solution that met the project’s stringent structural, safety, and quality assurance standards — contributing to the successful completion of one of Australia’s tallest residential conversions.
Project Details
General contractor: Probuild
Customer/Owner: Greenland Australia
Designer: Arup
Work Period: 2019
Solution: Post-tensioning Bar

GLOBAL LEADER IN SPECIALISED CONSTRUCTION SERVICES
Interspan delivers efficient, durable and sustainable solutions across bridges, tanks, buildings, ports and energy infrastructure — helping clients optimise structural performance, reduce costs, and lower embodied carbon in construction.
Our expertise spans post-tensioning, structural strengthening and specialised concrete technologies, applied across both new and existing structures.
By integrating engineering design, construction methodology and material efficiency, we deliver technically robust outcomes that enhance safety, service life and overall project value.